The temporary relocation site for traders affected by the fire at N'Zérékoré's Grand Marché is entering the home stretch. According to Pé Mission Gèmy, a community supervision technician at the National Agency for the Financing of Local Authorities (ANAFIC), the works are now more than 75% complete. The future temporary market is intended to accommodate some 1,500 traders pending the reconstruction of the central market destroyed by the blaze.
A fire that struck the economic heart of the Forest region
The fire broke out last June in the Grand Marché, the main trading hub of the capital of Forest Guinea. Thousands of vendors lost their stalls, shops and goods: nearly 3,000 traders were subsequently registered as victims. A few days after the disaster, the Minister of Trade, Industry and SMEs, Fatima Camara, visited the site, and a plot of around seven hectares was identified to rehouse the victims temporarily and, eventually, to host a modern market.

Development work was officially launched on 13 August at Tilépoulou, on land belonging to the Agriculture department, in the presence of the regional governor, Colonel Moussa Condé, the prefect, the mayor of the urban commune, Germain Tavaguez Kolié, representatives of the Chamber of Commerce and many traders.
Sheds, kiosks, latrines and a water tower
The project is led by the urban commune of N'Zérékoré as contracting authority and funded by the State through ANAFIC. It includes three metal sheds measuring 31.5 metres by 12, each designed for 300 to 400 vendors, mainly of condiments, as well as 80 metal kiosks measuring two metres by two. There will also be two latrine blocks of five cubicles each, a water tower, paved ground and street lighting. The works were divided into five lots, awarded to five companies after a restricted tender, under the supervision of a consulting engineer.

The total cost is estimated at 4.675 billion Guinean francs, according to ANAFIC. A first tranche of around 2.517 billion Guinean francs, slightly more than half of the budget, has already been transferred to the commune. The second tranche is still awaited to fund the completion of the works.
A timetable that has slipped

The site was originally due to be handed over on 29 September 2026. Almost two months later, no new handover date has been announced, and the traders' move will depend on the completion of the final finishing works. Local authorities are urging those affected to be patient, while many of them have been working since the summer in precarious conditions, at the roadside or on makeshift pitches.
Beyond this temporary site, the definitive reconstruction of the Grand Marché is still awaited. A new mission recently assessed the destroyed site, and local officials say work will begin soon, without giving a precise timetable.
For a city where the central market supports thousands of families and supplies a large part of the region, from Lola to Macenta, bringing this temporary market into service quickly is a major economic issue as the end-of-year holidays approach, traditionally the busiest period for trade.